Engineering & approvals
Hydrological studies, technical design and regulatory coordination completed with Uzbekistan’s energy authorities.

Final commissioning is underway. Official opening: 21 October 2026.
Hydrological studies, technical design and regulatory coordination completed with Uzbekistan’s energy authorities.
Water intake, penstock infrastructure and the turbine foundation have been rebuilt for long-term operation.
Cross-flow turbine, generator and control systems are being integrated and connected to the grid.
System testing, trial generation and handover lead into the official opening on 21 October 2026.
Latest photographs from Kashkadarya: powerhouse installation, grid works and landscaping ahead of the official opening on 21 October 2026.








US$4 million has now been fully invested and deployed into the restoration, equipment and commissioning of the SD Eco hydropower project.