SD Eco hydropower project in Kashkadarya, Uzbekistan
SD Eco / Progress

The next milestone.

Final commissioning is underway. Official opening: 21 October 2026.

Kashkadarya, Uzbekistan04 / 05
Project progress

From restoration
to generation.

21·10Official opening
01
Complete

Engineering & approvals

Hydrological studies, technical design and regulatory coordination completed with Uzbekistan’s energy authorities.

02
Complete

Civil infrastructure

Water intake, penstock infrastructure and the turbine foundation have been rebuilt for long-term operation.

03
Final stage

Equipment installation

Cross-flow turbine, generator and control systems are being integrated and connected to the grid.

04
Next

Commissioning

System testing, trial generation and handover lead into the official opening on 21 October 2026.

21October 2026
Opening day

US$4 million has now been fully invested and deployed into the restoration, equipment and commissioning of the SD Eco hydropower project.